What Penrith Council needs in your landscape plan
Part C6 of Penrith DCP 2014 explained: categories, documents and the checks after approval.
01 / 03 · Swipe →
Concept plans that answer Appendix F3
Levels, retained trees, planting schedules and maintenance notes, set out item by item.
02 / 03 · Swipe →
Ready for the implementation report
Penrith checks the built landscape before the OC. We draw plans your landscaper can build exactly.
03 / 03 · ← Swipe back
● Guide
Rules current to 25 November 2026 · Prepared by Dapple Landscape Design
Penrith City Council sorts landscape requirements by development category in Penrith DCP 2014, Part C6 Landscape Design. New single houses and complying development (Category 1) generally don't need landscaping information, though Council can ask for it. Other development under $2 million, such as dual occupancies, is Category 2 and needs a landscape concept plan. After construction, Council must approve an implementation report before the occupation certificate is issued.
3
landscape categories, set by development type and value
$2M
the value threshold between Category 2 and Category 3
12 months
after the OC, a maintenance report is due
01 —
Which Penrith landscape category is your development?
Part C6 places every development into one of three categories. The category decides how much landscape information you need to lodge.
Category / Includes / Landscape information
Category 1
Includes
New single dwelling houses; alterations and additions; complying development; other minor development
Landscape information
Generally not required, but Council may ask for a tree survey and/or a landscape concept plan
Category 2
Includes
All other work under $2 million that isn't in Category 1 (for example, most dual occupancies)
Landscape information
Landscape concept plan required; a landscape detail plan may be required
Category 3
Includes
Development over $2 million; sites with significant environmental or public domain considerations; work to a heritage item or in a heritage conservation area
Landscape information
Landscape concept plan and landscape detail plan required
Source: Penrith DCP 2014, Part C6, and Appendix F3, sections 4.4.2 and 4.4.3.
02 —
Who prepares a Penrith landscape plan, and what to lodge
Part C6 says landscape plans must be prepared by a suitably qualified consultant, and that members of accredited bodies (the Australian Institute of Landscape Architects, and the Australian Institute of Landscape Designers and Managers, now the Landscape Design Institute) should be engaged. Category 1 information, where Council asks for it, can be prepared by anyone as long as it's of a suitable standard.
Appendix F3 adds that every landscape plan must show the preparer's name, qualifications and membership details. Detailed content requirements for each document are in Appendix F3, section 4.4.
A landscape concept plan sets out landscaped areas, levels, retained trees and an indicative planting schedule, which is what Penrith's Appendix F3 asks for.
03 —
Landscape concept plan checklist (Appendix F3, 4.4.2)
For Category 2 and 3 developments, Penrith's landscape concept plan must include:
✓
A design vision statement for the site
✓
Landscaped areas, materials and finishes
✓
Contours, spot heights, finished levels, and retaining wall and fence details
✓
Retained trees with surveyed spot heights at the trunk base, numbered to match the arborist report, with tree protection zones referencing AS 4970
✓
An indicative planting schedule with botanical and common names, mature height, spread and container size, with street trees listed separately
✓
Maintenance specifications and the establishment period
✓
An accessibility statement for open space areas
✓
A replacement strategy for plants that fail
✓
Erosion and sediment control details where the scale of works requires them
A landscape detail plan (section 4.4.3) adds construction-level detail. It's required for Category 3 and may be required for Category 2.
04 —
Penrith tree reports
Arboricultural Survey Report (Appendix F3): prepared by an arborist, covering trees over 5 m tall, including trees on adjoining land within 3 m of the boundary.
Tree Management Plan (Appendix F3): must be in place before site works start.
05 —
Plant selection rules (C6, 6.1.2)
Plants must suit the site's soil, aspect, drainage and micro-climate.
Native species are encouraged. Exotic species may be considered if they fit the existing landscape character and are unlikely to spread into bushland.
Sites next to remnant bushland should use species found in that bushland, preferably from local provenance stock.
Noxious and listed environmental weeds must not be used (Appendix F4).
Plant selection should consider bushfire risk, and planting should mix trees, shrubs and groundcovers.
Our Plant Finder lets you filter plants for Western Sydney conditions.
06 —
What happens after a Penrith approval
Penrith spells out landscape checks after the DA in unusual detail. Part C6 sets out the sequence:
01
Conditions of consent
Conditions may require post-approval landscaping reports and/or a landscaping bank guarantee.
02
Construction
A landscape contractor builds the approved works. Council says they should be qualified, preferably a member of the Landscape Contractors Association of NSW.
03
Implementation report
When works are complete, Council must approve a report certifying the landscaping matches the consent and Part C6.
04
Occupation certificate
Issued once the implementation report is accepted and other Council requirements are met.
05
Maintenance report
Due 12 months after the occupation certificate, confirming the works still match the consent and plants are established. Larger or visually prominent developments may also need a 3-year report.
Plan for the implementation report from day one
A plan that's easy to build is easier to certify. We specify plant sizes, quantities and finishes clearly so your landscaper can build exactly what was approved.
Built as approved: Penrith checks the finished landscaping before the occupation certificate is issued.
Fixed-quote landscape plans
Building or subdividing in Penrith?
We prepare Penrith landscape concept and detail plans to Part C6 and Appendix F3, and can help with the implementation report.
Frequently asked questions
Does a new house in Penrith need a landscape plan?
New single dwelling houses are Category 1 under Part C6, which generally doesn't require landscaping information. Council can still ask for a tree survey or landscape concept plan where a site needs it.
Is a dual occupancy Category 2 in Penrith?
Category 2 covers all work under $2 million that isn't listed in Category 1. Dual occupancies aren't listed in Category 1, so most fall into Category 2 and need a landscape concept plan.
Who can prepare a Penrith landscape plan?
A suitably qualified consultant. Council says members of the Australian Institute of Landscape Architects or the Australian Institute of Landscape Designers and Managers (now the Landscape Design Institute) should be engaged.
What is a landscape implementation report?
A report Council must approve after the landscaping is built, certifying that it matches the consent and Part C6. The occupation certificate can't be issued until it's accepted.
Sources and review
Also referenced: Penrith DCP 2014 Appendix F3 DA Submission Requirements.
JS
Prepared by Dapple Landscape Design, led by designer Julian Saw (member, Landscape Design Institute). This guide is general information, not planning or legal advice. Councils amend their development control plans regularly, so confirm the current controls for your lot with council or your certifier before lodging.